|
After three years of construction
clogging main streets in town, there is
only one possible project in 2007, the
Franklin Street roundabouts and medians.
Even that is not definite
because detailed engineering must be
done before the project can be sent out
for bids. If it does go forward, Deputy
Town Manager Roe O’Donnell said this
week, it will be late summer before
construction can begin.
O’Donnell said the
engineering plans will be for the entire
project with roundabouts at Holding
Avenue and Elm Avenue and medians from
Holding to Wait Avenue. However, he
said, the cost of the project will
probably mean only part of the project
can be done with the bond money from
2005.
That would include the base
bid – the two roundabouts with end
treatments that would be monument signs
for downtown – and the landscaped median
and sidewalks from Holding to Elm. If
the bids are low enough, they can add
the median from Elm to Wait. As for a
median from the N.C. 98 bypass to
Holding, “We do not contemplate doing
that now.”
The cost for this project,
part of the Renaissance Plan for the
heart of the town, has been rising
faster than a hot air balloon.
It began at $2.4 million
when voters approved the $9.5 million
streets and sidewalk bonds in the spring
of 2005. Late last year O’Donnell said
new estimates put the cost at $4.2
million, and Finance Director Aileen
Staples sold that amount of bonds in the
fall for the project.
By the time of the town
board’s planning retreat on Jan. 12, the
cost was at $5.66 million. O’Donnell
said he could reduce that by $600,000 if
the street is built with street lights
in the median rather than on the sides.
The red tape at the Wake
Forest Fire Department’s Station #1 on
Elm does indicate the extent of the
right-of-way and construction easements
needed for the roundabout.
“It’s going to be standard
full-sized urban roundabout,” O’Donnell
said, and the one at Holding will be the
same size. The town’s first roundabout,
the one at South Main and South Avenue,
is the minimum size for a compact urban
roundabout. It had to be compact to fit
between the historic properties.
The size of the roundabout
at Elm, as the red tape shows, means the
fire department has to find a new
location for the Jimmy Keith memorial
statue.
While the detailed
engineering for Franklin Street is
underway, O’Donnell is also assembling
an estimate of what it would cost to
widen Ligon Mill Road from South Main
Street west past a side entrance to
Wal-Mart.
Parker & Orleans Home
Builders, the developers of Reynolds
Mill subdivision, plan to remove the
sewer pump station where Ligon Mill now
dead ends, grade the right-of-way for
the street to a four-lane width and pave
two lanes to the intersection with
Caveness Farm Avenue.
Opening that road – and
extending it later to the N.C. 98 bypass
– “will take some pressure off South
Main Street. That, along with the
Franklin Street extension when it’s
completed,” O’Donnell said.
The Franklin Street
extension, which would be built by the
Holding Village developers if the
project is approved by the town, “will
give people in Heritage another way to
go north rather than having to come out
onto South Main to go north.”
At the retreat, the town
commissioners agreed they might use the
$1 million earmarked in the bond issue
to widen South Main from Rogers Road to
Forbes Road for the Ligon Mill project.
South Main residents had strongly
opposed the town’s plan for four lanes
and a 4-foot concrete median.
Ligon Mill will be built as
a four-lane road with a median with turn
lanes in the median. The town’s
transportation plan calls for it to
reach and cross Durham Road near the
Wake Forest Business Park and
McDonald’s.
But where Ligon Mill meets
South Main, O’Donnell said, it will be
widened to six lanes to accommodate two
left turn lanes. The two full lanes
leading east foretell a future when that
section of Ligon Mill will also be
completely widened to four lanes.
The rising costs of road
construction mean that three projects in
the 2005 bond issue may be delayed until
another bond issue. Along with the $1
million for South Main and $2.4 million
for Franklin Street, voters were told
the money would pay $3.3 million to
build part of the North Loop, $2.2
million to widen Stadium Drive to three
lanes from Rock Spring Road to Capital
Boulevard and $600,000 to build a
sidewalk on North White Street.
A decision has not been made
about any of the $9.5 million except for
the Franklin Street project. During the
retreat, Mayor Vivian Jones said they
want to see the North White Street
sidewalk built from the current bond
monies, and Commissioner David Camacho
said he wants the North Loop built to
help spur economic development in the
northeast part of town. |