|
Commissioner Margaret Stinnett spent a
large part of the morning at the town
board’s Friday retreat insistently
questioning why the cost of the top
three road and street projects in the
2005 bond issue keeps rising and when
they will be done.
The three are the Franklin
Street roundabouts and median, widening
South Main Street from Forbes Road to
Forestville Road, and a sidewalk along
North White.
The bond issue presented to
voters was to build Franklin Street for
$2.4 million. The current estimate is
$5.2 million with the landscaping,
engineering, lighting and underground
utilities.
“Where are the extra three
million bucks coming from?” Stinnett
asked.
“From the bond issue,”
Deputy Town Manager Roe O’Donnell said.
“I honestly think by the
time we pay for these three projects the
bond money will be gone,” Stinnett said.
The $9.5 million approved by
voters was for $3.3 million to build
part of the North Loop, $1 million to
widen South Main Street to five lanes
from Rogers Road to Forbes Road, $2.2
million to widen Stadium Drive to three
lanes from Rock Springs Road to Capital
Boulevard, $2.4 million for Franklin
Street and $600 for the North White
Street sidewalk.
Town Manager Mark Williams,
Mayor Vivian Jones, Commissioner David
Camacho and O’Donnell said, at various
times, the problem is that totally
unforeseen inflation in construction
costs began soon after the bonds were
passed.
“The cost of construction
has skyrocketed over the past two years
because of hurricanes and the material
we are selling to China,” Williams said.
Jones called the inflation
extremely extraordinary. “It’s something
that nobody could predict.”
“Next time we do a bond
issue we need to be absolutely certain
which projects we want to do and how to
do them,” Williams said. That would
include having engineering and other
planning done so “we can speed them up
and get them done faster.”
He mentioned South Main
Street where neighbors shot down the
town’s proposal for four travel lanes
divided by a concrete median from Rogers
to Forbes.
The town is planning a
different project, adding a lane between
Forbes and Forestville to make two
travel lanes and a turn lane.
When will construction start
there, Stinnett asked.
“It depends on the
right-of-way. We want to acquire as
little as possible,” O’Donnell said. The
design is just beginning. When it is
complete, the engineer will decide what
right-of-way needs to be purchased.
Next came the North White
Street sidewalk, and O’Donnell said it
is under design. “We may be able to do
that job ourselves. We are very
proficient in sidewalk construction.”
The question became how the
sidewalk should be designed – with or
without curb and gutter -- because the
east side of North White has a number of
drainage ditches. The west side is not
possible because of the railroad and its
right-of-way.
“Do you just want a sidewalk
that runs all over the place?” Planning
Director Chip Russell asked. His
suggestion: “Do a project and do it the
best way you can.”
It will take longer to do
the larger job with curb and gutter,
Commissioner Frank Drake said. “Which do
the residents want?”
“I just keep hearing that
there is no way for kids to get to
Flaherty Park,” Stinnett said.
“The quickest way to get the
sidewalk is for us to do it. If you want
curb and gutter, we can’t do that
ourselves,” O’Donnell said.
A bit later, Commissioner
Stephen Barrington chimed in to say he
wants the curb and gutter. “I don’t want
us to have to redo it.”
O’Donnell also said the town
crews can build the desired sidewalk to
Ailey Young Park, but there are some
“real tough issues,” Williams said.
“There are houses right on the road. It
comes down to a political decision.” |