           (Road roundup is a standing feature of the Gazette, designed to keep people informed about the progress of the various street and road projects in town. New projects or updated projects will appear at the top of each week’s column in blue.)

            There is bad news this week for local commuters.   

            The draft Transportation Improvement Plan (TIP) for 2007-2013 delays two local projects, the third leg of the N.C. 98 bypass in Wake Forest and the widening of U.S. 401 from Ligon Mill/Mitchell Mill to Louisburg.

            The draft is due to be released today (Sept. 6), The News & Observer reported, and there will be public hearings before it is adopted, but few changes are anticipated. The delays are blamed on the escalating cost of almost every road-building component – steel, concrete and asphalt.

            The contract to build the bypass was due to be let in 2007 with work beginning that same year. The draft pushes that schedule back a year to 2008.

            The work on U.S. 401 is also being delayed a year from 2008 to 2009. The first leg to be built will be from Ligon Mill/Mitchell Mill to Louisbury Road just south of Rolesville, and the bypass to the east of Rolesville was to follow. Now the draft reportedly says “most construction unfunded through 2013.”

            The third leg of the bypass – from Capital Boulevard to Thompson Mill Road where it will rejoin N.C. 98 – is a top priority of CAMPO (the Capital Area Metropolitan Planning Organization), Mayor Vivian Jones said recently. She said the funds for the final section come from the federal government for surface transportation.

            “The metropolitan planning organizations have the authority to decide where that money is spent, and those funds are assigned to CAMPO,” Jones said. CAMPO (Capital Area Metropolitan Planning Organization) has designated those funds to finish the bypass.”

            That final section of the bypass will also include a realignment of Falls of the Neuse Road to meet Thompson Mill and closing a section of N.C. 98 (Durham Road) between Capital Boulevard and Thompson Mill.

            The Gazette will have more about the plans, the local response and the public meetings next week.

* * * *

            Please do not strain your eyes watching for Rea Contracting to begin patching and repaving South Main Street (U.S. 1-A) and N.C. 98 (Durham Road and Wait Avenue). The crews will not appear until sometime in September.

            Steve Leonard, the resident engineer for this part of the state DOT’s Division 5, said Rea had “overextended themselves” and had done a lot more patching than the resurfacing crews could cover.

            Rea had a number of contracts to repair and repave area roads this summer.

            The work in Wake Forest, estimated            to cost $362,000, should take about three weeks.

* * * *

            The web site for the U.S. 1 (Capital Boulevard) Corridor study has been updated. You can find it http://www.ncdot.org/~us1study.

            People at the July 27 public meeting in Living Word Family Church learned the project is estimated now at $400 million.

            Also go to http://www.ncdot.org/doh/preconstruct/

tpb/shc/studies/US1 for information about all the corridor studies underway in the state. A lot of local people use U.S. 70 from Raleigh to Morehead City, and of course it is a hurricane or disaster evacuation route. Although the Clayton bypass ($179 million) is underway and work on the Goldsboro bypass ($234 million) is expected to begin in 2008, none of the other bypass projects are funded.

* * * *

            As the Gazette reported recently, the estimates now for the Franklin Street roundabouts, median and landscaping have risen from the $2.4 million projected last year and included in the $9.5-million bond issue to $4.2 million.

            Finance Director Aileen Staples intends to sell $4.2 million in those bonds in September along with either $1 million or $1.5 million to widen South Main Street to either four or five lanes from Rogers Road to Forbes Road. A four-lane width would save on right-of-way acquisition costs but would mean a concrete median.

            O’Donnell has said the town may not be able to afford the entire cost of the Franklin Street project at one time, and the bids will be structured to allow the town to construct one section at a time. The project is part of the town’s Renaissance Plan.

            The increased cost, O’Donnell said, were mostly because of high oil prices.

            The engineers and staff at Kimley-Horne Associates are finishing plans for the street, incorporating ideas from the July 31 public meeting. The next step will be purchasing right-of-way and then sending out a request for bids.

            The other projects in the 2005 street bond issue were 1) construction of part of the North Loop at $3.3 million, 2) widening Stadium Drive to three lanes from Rock Springs Road to Capital Boulevard at $2.2 million and 3) building a sidewalk on North White Street from Juniper Avenue to Flaherty Park at $600,000.

* * * *

            The North Carolina Department of Transportation plans to put up signs for a truck route through Wake Forest, Deputy Town Manager Roe O’Donnell said recently. The signs will probably be erected at the east and west approaches to town on N.C. 98 and on South Main Street where it nears the bypass.

* * * *

            In the future, there will be at least nine sets of traffic signals on the 4.8-mile N.C. 98 bypass.

            We already have those at Jones Dairy Road and business N.C. 98 (Wait Avenue), those at South Main Street and the three sets at Capital Boulevard.

            Between Jones Dairy and South Main, there may be signals where Heritage Lake Road intersects but does not cross the bypass, and it is very likely there will be signals at the intersection when Franklin Street is extended into Heritage.

            To the west of South Main, there will certainly be signals when Ligon Mill Road is built to meet or cross the bypass.

            In the third section, we can count on at least one set of signals in Wakefield, another at the realigned Falls of the Neuse Road, and a third at Thompson Mill Road.

            Depending on the development of the land and whether the northern and southern portions of Siena Drive are connected, there could be another set of signals.

            If you want to keep abreast of local road projects, you can go to the town’s web site at http://www.wakeforestnc.gov/

roadandconstructionprojects.aspx.

* * * *

            A subscriber posed this question: Was it ever considered to turn the entire two-lane road around the seminary (Front Street, North Avenue, North Wingate Street, South Avenue) into a one-way road going all the way around the seminary? This would create a giant rotary, utilizing its wonderful benefits at each of the five or six major roads which feed into this group of roads today?

            Well, yes, that has been considered, but O’Donnell said it had been put on the back burner by a mutual decision by the town board and DOT “until we can see what effect taking the traffic on the bypass has.”

            DOT, in fact, had even constructed a computer simulation with smaller roundabouts at different points – the underpass, Wingate and North – and in one demonstration showed little bugs of vehicles running round and round at various speeds under various conditions.

            That simulation, however, only dealt with vehicles and did not touch the way students at Southeastern Baptist Theological Seminary cross North Wingate constantly to get to and from the parking areas and the Ledford Student Center. “The pedestrians on Wingate have to be accommodated,” O’Donnell said.

 