May 10, 2006

  Volume 4, Number 19

Published in Wake Forest, NC

  Carol Pelosi, Publisher and Editor
 
 
 
 
 
 
Archives
Where To Find It
Town Meetings
Club Meetings
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 Road Roundup

           (Road roundup is a standing feature of the Gazette, designed to keep people informed about the progress of the various street and road projects in town. New projects or updated projects will appear at the top of each week’s column in blue.)

            S.T. Wooten, the contractor for the N.C. 98 bypass, was a day or two later than its planned date of Monday, May 8, in closing the entrances to Retail Drive and Galaxy Drive from Capital Boulevard. They were not closed Tuesday, but by Wednesday noon traffic was using the temporary entrances to the north and dump trucks and bulldozers were building up and compacting the ramps to the bypass.

            Traffic on Capital was restricted to one lane in each direction Wednesday and there were long lines.

            Wooten still has a target date of June 7 to open the bypass to traffic with a target completion date of July 7.

            Wooten’s contract for $21,211,427 was let in late 2003 and work began early in 2004.

            If you want to keep abreast of road projects, you can go to the town’s web site at www.wakeforestnc.gov/residents/engineering_

roadandconstructionprojects.aspx.

 

* * * *

            If you thought the widening of South Main Street took forever and have doubts about seeing the roundabout at the seminary completed in your lifetime, you are not alone.

            Kimley Horn and Associates, the consulting firm the town has used for many street projects, did the engineering work and construction observation for both. They will ask the town board next Tuesday for additional money because the construction has been drawn out past the estimated time and the KHA staff has done much more construction observation than anticipated.

            The state has let a contract for the South Main resurfacing, including milling out and replacing some of the old pavement, but there is no date yet for the work.

* * * *

            Deputy Town Manager Roe O’Donnell says the plans for the roundabouts and median on Franklin Street are about 70 percent complete. Once they are 90 percent complete and have a nod of approval from the state Department of Transportation, he and his staff will hold a public meeting, asking for comments.

            A third roundabout is in the plans in addition to the ones at Elm and Holding avenues. This would be at the intersection of East Owen Avenue, which currently ends between the police station and town hall annex. O’Donnell says the town plans to extend the street and use some form of a bridge or culvert to take it over two small streams.

* * * *

            Put this date on your calendar if you care about Capital Boulevard (U.S. 1) – Tuesday, June 27. The second public meeting on the U.S. 1 Corridor Study will be held that day at Triangle Town Center at a time to be announced later.

* * * *

            Work on the bridge on Stadium Drive appears to be on schedule, judging by the removal of the old bridge, the piles of dirt on either side of Richland Creek and the amount of equipment Balfour Beatty Construction has on site.

            The new bridge – 40 feet wide – should be complete by the end of August. It will be wide enough for the planned three traffic lanes to be constructed at some future date.

            Balfour Beatty’s contract with the state Department of Transportation is for $1.1 million.

* * * *

            For a couple weeks, Road Roundup had been saying the roundabout at South Main and South Avenue (N.C. 98) would soon allow traffic to enter, merge and exit without stop signs.

            It finally happened, albeit with a small forest of orange barrels and at least three, maybe four, men directing vehicles through the maze on May 1. No more stop signs, but some confusion. Mark Roberts documented the confusion on the part of some drivers, many of them using cell phones.

            The interior circle, destined to be bricked and landscaped, is unfinished, and the last word was it would take at least another two months before it is complete.

* * * *

            Wake Forest, with the help of federal funds funneled through the state, is about to build two sidewalk sections near the seminary campus, but the first step will be to remove some trees in the way.

            The sidewalks, each 5 feet wide, will be 480 feet on the east side of Front Street from the Roosevelt Avenue underpass to the intersection of Front and North Avenue, and 1,200 feet on the south side of Stadium Drive from North Wingate Street to past Judson Drive.

            Town crews will remove one large oak at Front and North. They were to remove some trees on the seminary property, but a Raleigh landscape firm, Realiscape, asked Southeastern Baptist Theological Seminary for the seven small maples and 13 crape myrtles. The firm will dig up the trees and plant them elsewhere.

            “It will give us a chance to plant canopy trees,” planner Lisa Potts said. She plans 21 shade trees along the Durham Road sidewalk, a mix of oaks, maples and elms. “When you’re walking to class, you want some shade.

            The town has a $99,800 grant through the North Carolina Department of Transportation Enhancement Program. It was given on a cost-reimbursement basis. The town has to pay the full cost for engineering, design and construction and then can be reimbursed for up to 80 percent of the cost. The town’s share will be $19,960. The state is then reimbursed by the federal government.

            Sidewalk construction is planned to begin May 15 after the trees are removed and transplanted.

* * * *

            Work has begun on the next section of the Smith Creek Greenway, this one 1,500 feet from the Smith Creek Soccer Center to Rogers Road. A 60-foot bridge will link the new section with the existing greenway section in the soccer center.

            The Smith Creek Greenway, which will eventually be a 7-mile corridor from the Franklin County line to the Neuse River, is the town’s number-one greenway priority. Along with the sections described above, there is an existing paved section that runs three-fourths of a mile from Burlington Mills Road to the river. The town has acquired much of the right-of-way for other sections through negotiations with subdivision developers.

* * * *

            When the N.C. 98 bypass is complete from Jones Dairy Road to Thompson Mill Road, there will be nine traffic signals on the 4.8-mile limited-access road.

            There will be the set at Jones Dairy Road and business N.C. 98 (Wait Avenue); a set where Heritage Lake Road intersects but does not cross the bypass (and you can already see the clearing for the road); a set at Franklin Street but not, perhaps, until that street is extended into Heritage; the current signals at South Main Street; a set at Ligon Mill Road when it is extended; a set at Capital Boulevard; and signals in Wakefield, at the realigned Falls of the Neuse Road, and at Thompson Mill.

            Planning Director Chip Russell said there is still a question whether Siena Drive – which has sections north and south of the bypass already – will be connected. That could be the tenth intersection with traffic signals.

* * * *

            The traffic signal on Rogers Road at the entrance to Heritage Elementary and Heritage Middle School is still slated to be installed this spring. Mayor Vivian Jones and other town commissioners vigorously lobbied for the signal, and state Sen. Neal Hunt was instrumental in getting it approved by DOT.

 
Copyright © 2006
The Wake Forest Gazette
All Rights Reserved

 

 

 
 
WRAL OnLine Weather
 
On-Time Traffic