|
The Wake Forest water treatment plans is
now pumping 700,000 to 800,000 gallons a
day for town customers, and it will soon
be operating 24 hours a day, seven days
a week, pumping out 1.8 to 1.9 million
gallons a day.
The City of Raleigh is
continuing to operate the G.G. Hill
plant because of this spring’s severe
drought, even though the merger
agreement signed last year specified it
would be closed.
“The extra water will help”
the drought situation, Ron Horton said.
Horton oversees Raleigh’s suburban water
and sewer systems: Wake Forest,
Rolesville and Garner.
The main reason, though, for
changing to the 24/7 operation, Horton
said, is to train employees who will be
transferred to the planned
20-million-gallon-a-day plant near
Garner that will draw water from lakes
Benson and Wheeler. Horton said the
Raleigh City Council has just approved a
midyear budget package adding six
employees at the Wake Forest plant.
Horton said Raleigh still
plans to shut down the Wake Forest plant
at some point.
“If we were not in a drought
situation we would have been able to
shut down that plant. Gallon-wise, it
costs a lot more to produce water out of
that plant,” Horton said.
Jessee Walker, the
operations supervisor at the Wake Forest
plant, said the Smith Creek reservoir
that provides the water, is in good
shape. “It’s full to the brim now. It’s
a good reservoir.” Walker said that
during last year’s severe drought the
reservoir was down 4 feet from full. It
is supplied by Smith Creek, which rises
in Franklin County, and by springs.
The Garner plant, which has
already been named for Dempsey Benton,
Raleigh’s former utilities director, has
been designed and is ready for bid,
Horton said, but progress has been held
up for an environmental assessment.
In other news about
Raleigh’s operation of the Wake Forest
system, Horton said the water and sewer
crews are settled into the former Chris
Leith Kia dealership on Star Road. The
crews service the Wake Forest and
Rolesville systems, and in the future
will also service Wakefield, Horton
said. It will also be named the North
Raleigh Operations Center at some future
point.
The merger agreement spelled
out an estimated $16 million in
improvements to Wake Forest utilities.
(The purchase of a million gallons of
water capacity added $3 million more.)
“We’ve started the design of
the water system improvements,” Horton
said, and the plans are about 90 percent
complete. The city needs to get
easements and approval to cross under
the CSX rail line. The new lines will
improve water pressure and loop the
system better, Horton said. Areas across
the north side of Wake Forest have
experienced long-standing low water
pressure.
“There is one project in
Raleigh that will eventually help with
the pressure,” Horton said. That is a
24-inch water line from the E.M.
Johnston Water Treatment Plant on Falls
of the Neuse Road that will feed the
1-million-gallon water storage tank that
was just completed. It stands on Falls
near its intersection with Old N.C. 98.
Once the 24-inch line is
complete, the water line through
Wakefield will have to be connected to
the Wake Forest system at a point along
U.S. 1 (Capital Boulevard).
Wake Forest began work on
that connection in May of 2004 but was
halted by Raleigh because of low
pressure problems in Wakefield.
“We’ve started on the
sanitary sewer system evaluation, and
we’ve started – though we’re not very
far along – on the Smith Creek
wastewater treatment plant upgrades,”
Horton said.
The upgrades for the Smith
Creek plant will increase its capacity
“and probably wind up changing the
method of treatment,” Horton said. The
thinking is that the solids will be sent
down the pipe along the Neuse River to
the city’s Neuse River Wastewater
Treatment Plant.
Also, “We’re doing a
[wastewater] reuse master plan,” Horton
said, and the Smith Creek plant is being
evaluated as part of that master plan.
The treated wastewater from the Smith
Creek plant could be used for
irrigation, in cooling towers and in
other industries that do not need
potable water. |