|
(Road
roundup is a standing feature of the
Gazette, designed to keep people
informed about the progress of the
various street and road projects in
town. New projects or updated projects
will appear at the top of each week’s
column in
blue.)
Wake Forest, with the help of federal
funds funneled through the state, is
about to build two sidewalk sections
near the seminary campus, but the first
step will be to remove some trees in the
way.
The sidewalks, each 5 feet
wide, will be 480 feet on the east side
of Front Street from the Roosevelt
Avenue underpass to the intersection of
Front and North Avenue, and 1,200 feet
on the south side of Stadium Drive from
North Wingate Street to past Judson
Drive.
Town crews will remove one
large oak at Front and North. They were
to remove some trees on the seminary
property, but a Raleigh landscape firm,
Realiscape, asked Southeastern Baptist
Theological Seminary for the seven small
maples and 13 crape myrtles. The firm
will dig up the trees and plant them
elsewhere.
“It will give us a chance to
plant canopy trees,” planner Lisa Potts
said. She plans 21 shade trees along the
Durham Road sidewalk, a mix of oaks,
maples and elms. “When you’re walking to
class, you want some shade.
The town has a $99,800 grant
through the North Carolina Department of
Transportation Enhancement Program. It
was given on a cost-reimbursement basis.
The town has to pay the full cost for
engineering, design and construction and
then can be reimbursed for up to 80
percent of the cost. The town’s share
will be $19,960. The state is then
reimbursed by the federal government.
The tree removal and
transplanting will begin within two
weeks, and sidewalk construction is
planned to begin May 15.
* * * *
There is a new date for the
next leg of the N.C. 98 bypass
to open, but it still may change if
there is bad weather – no one could
complain about rain – or some other
holdup.
The state Department of
Transportation has told the town that
the second leg, from South Main Street
to Capital Boulevard, will open to
traffic June 8.
A month before the
contractor, S.T. Wooten will close both
Retail and Galaxy drives on May 8 after
different outlets from Capital Plaza
Shopping Center (Home Depot and Target)
and Lowe’s Home Improvement,
respectively, have been completed.
There will still be minor
work from June 8 until July 7, the
tentative date to complete the project.
The contract for $21,211,427
was let in late 2003 and work began
early in 2004.
If you want to keep abreast
of road projects, you can go to the
town’s web site at
www.wakeforestnc.gov/residents/engineering_
roadandconstructionprojects.aspx.
* * * *
South Main Street
from Capital Boulevard to the N.C. 98
bypass will be paved at some point this
spring and summer. The state has let
contracts for paving projects in
Northern Wake County, and the repaving
of N.C. 98 from Capital
Boulevard to the roundabout under
construction at the seminary is also on
the list. The contractor will not pave a
portion of South Main between Rogers
Road and Forbes Road because the town
plans to widen that section to five
lanes this year. Work on that section is
expected to begin this fall just after
motorists have experienced a short
respite from work zones.
* * * *
The roundabout
where South Main Street meets South
Avenue (N.C. 98) at the seminary should
open to allow traffic to enter, merge
and exit without stop signs this week.
There is still work to be done on the
interior circle, and it will take
another 10 weeks to complete it.
* * * *
Stadium Drive is closed to
through traffic until the end of August
while Balfour Beatty Construction Inc.
tears down the existing bridge and
builds a new one 40 feet wide. The
contract with the state Department of
Transportation is for $1.1 million.
The DOT web site gives
directions about using Harris Road and
North Main Street as the detour although
another route is Durham Road (N.C. 98).
* * * *
Work has begun on the next section of
the Smith Creek Greenway, this one 1,500
feet from the Smith Creek Soccer Center
to Rogers Road. A 60-foot bridge will
link the new section with the existing
greenway section in the soccer center.
The Smith Creek Greenway,
which will eventually be a 7-mile
corridor from the Franklin County line
to the Neuse River, is the town’s
number-one greenway priority. Along with
the sections described above, there is
an existing paved section that runs
three-fourths of a mile from Burlington
Mills Road to the river. The town has
acquired much of the right-of-way for
other sections through negotiations with
subdivision developers.
* * * *
The North Allen Road
sidewalk is finished, and the street has
been widened and resurfaced. New curb
and gutter has also been added. The
sidewalk provides access to Juniper
Avenue, which has a sidewalk that
extends to Ailey Young Park.
One of the town’s next major
sidewalk projects is one along North
White Street to Flaherty Park.
* * * *
The town is still drawing
plans for the two roundabouts on
South Franklin Street at Holding
Avenue and Elm Avenue. There will be a
public meeting for comments when the
plans are about 70 percent complete.
* * * *
When the N.C. 98
bypass is complete from Jones
Dairy Road to Thompson Mill Road, there
will be nine traffic signals on the
4.8-mile limited-access road.
There will be the set at
Jones Dairy Road and business N.C. 98
(Wait Avenue); a set where Heritage Lake
Road intersects but does not cross the
bypass (and you can already see the
clearing for the road); a set at
Franklin Street but not, perhaps, until
that street is extended into Heritage;
the current signals at South Main
Street; a set at Ligon Mill Road when it
is extended; a set at Capital Boulevard;
and signals in Wakefield, at the
realigned Falls of the Neuse Road, and
at Thompson Mill.
Planning Director Chip
Russell said there is still a question
whether Siena Drive – which has sections
north and south of the bypass already –
will be connected. That could be the
tenth intersection with traffic signals.
* * * *
The traffic signal on
Rogers Road at the entrance to
Heritage Elementary and Heritage Middle
School is still slated to be installed
this spring. Mayor Vivian Jones and
other town commissioners vigorously
lobbied for the signal, and state Sen.
Neal Hunt was instrumental in getting it
approved by DOT. |