|
Stadium Drive will be closed from April
3 to Aug. 24 while a contractor for the
state Department of Transportation
rebuilds the bridge over Richland Creek.
The closure will
inconvenience students at both Wake
Forest-Rolesville High School and
Southeastern Baptist Theological
Seminary, but Wake Forest firemen feared
it might have much more serious
consequences if there were a fire,
vehicle accident or serious health
problem on the west end of Stadium or in
the part of town usually reached by that
route.
Therefore, Fire Chief David
Williams Jr., with the help of the
seminary, hopes to be able to station a
fire truck and at least two firefighters
on the west side of the bridge.
“We are still discussing
that,” Williams said Tuesday, saying
that the fire department board has not
finalized the plans yet. He has reached
an agreement with the seminary to use a
vacant apartment in one of the apartment
complexes the seminary owns and pay only
utilities.
Wake Emergency Medical
Services is counting on the Wake Forest
Fire Department to provide
first-responder service.
Tony Crawford with Wake EMS
said Tuesday they will continue to
station their ambulances on South
Franklin Street. “The first-responders
will get there. It will not increase our
response time by more than two or three
minutes.”
The contract for the bridge
reconstruction was won by Balfour Beatty
Construction Inc. for $1,141,692. Deputy
Town Manager Roe O’Donnell said the
bridge will be built to a 40-foot width
or three lanes wide.
Widening Stadium Drive to
three lanes “with interspersed median
trees” to resemble the section of North
Main Street just north of the seminary
is the number six project on the town’s
transportation plan adopted in 2003. The
cost was then estimated at just over $2
million.
Project number one was
hastening work on the N.C. 98 bypass.
Project number two was the
South Main widening which will be
complete when it is resurfaced from
Capital Boulevard to the N.C. 98 bypass
this summer.
Project number three is the
extension of Ligon Mill Road on the west
side of South Main. The road currently
ends just to the west of Wal-Mart and
cannot be extended there until a new
sewer line is laid and a sewer pump
station in the right-of-way can be
dismantled. The transportation plan
calls for the construction of a
four-lane section from Caveness Farms
Road north to the bypass to be done at
developers’ expense and a three-lane
section from the bypass to Stadium Drive
at an estimated cost of $7 million.
Project number four is the
North Loop, envisioned as three lanes,
from North Main Street to East Wait
Avenue. The town will contract this week
for preliminary engineering of the
section between North Main and North
White Street, which includes crossing
the CSX Railroad line. The contract
stipulates planning for at-grade
crossings for the streets and the
railroad. Planning Director Chip Russell
said Tuesday the reason for letting the
contract now is to establish a
right-of-way so that when or if a
high-speed rail line is built through
town that entity will have to build the
elevated crossing that will be required.
Last May Wake Forest voters
approved two bond issues -- $7 million
for parks and recreation and $9.5
million for streets and sidewalks. Part
of the $9.5 million was $3.3 million to
build part of the North Loop from North
Main to North White, and the bond issue
specified building a bridge over the
railroad line and North White.
Project number five is
extending Franklin Street from the
bypass to Rogers Road at a cost of $5
million. That was not included in the
bond issue because Heritage Lake Road is
being extended to the bypass – it will
intersect but not cross it – just to the
east of Franklin and will carry traffic
between downtown and Rogers and
Forestville roads. |